Case Studies
Study 61001 - Drain System Install
Problem: This commercial property owner called Pier Masters because water was entering the building between the foundation wall and the slab.
Solution: The Field Consultant visited the property and made the following determination: mitigate the water by installing a
foundation drain and drain mat along the foundation wall.
Before:
After:
Study 70001 - Retaining Wall
Problem: The new owners of this residence inherited a rubble stone retaining wall. They wanted something more professional and stable.
Solution: They called Pier Masters to design a two-tiered modular wall and to redirect drainage to allow for more landscaping. A back patio retaining wall was also designed to prevent further soil erosion. The end result was exactly what the homeowners were seeking.
Before:
After:
Study 70002 - Retaing Wall
Problem: A local Homeowners Association was experiencing deteriorating timber retaining walls that required complete replacement.
Solution: Pier Masters engineered a more structurally sound solution by constructing modular block walls. The new block walls have a more pleasing curb appeal and design while still providing a structural and permanent foundation.
A drainage issue was addressed that was affecting the growth of some of the Association’s decorative trees. The trees were saved by integrating a drainage system behind the new block retaining walls and managing the run-off water.
Pier Masters successfully gave this property an effective and beautiful make-over.
Before:
After:
Study 21002 - Commercial Piering
Problem: This beautiful historic Library Visitor’s Center was constructed of native limestone. Unfortunately the building’s history included settlement that created cracks in walls and the foundation.
Solution: Pier Masters’ crew work hard to install 26 piers to stabilize the building and five more piers to help lift the building. The crew works just as hard to restore the site to as close to its original state as possible…
Before:
After:
Study 21003 - School Foundation Settlement
Problem: The soil underneath the slab of a large portion of the elementary school had settled over many years leaving large voids. Several classrooms were showing slab settlement of up to 3-4 inches.
Solution: AB Chance/Atlas Helical Slab Piers were installed using portable equipment for easy access. The piers were installed through an 8-10 inch hole in the slab and spaced at a pre-determined engineered pattern. A total of 443 piers were installed and the slab was returned to its original elevation. No void filling was required after the installation was complete.
Before:
After:
Study 21005 - Commercial Piering - Bank
Problem: Cracking sheetrock on the walls and large gaping floor cracks were major concerns with this building.
Solution: Pier Masters stabilized the bank by installing 19 Atlas Resistance Piers to its perimeter.
Before:
After:
Study 21004 - School Foundation Settlement
Problem: With gapping cracks in its exterior walls, the foundation cracking, as well as interior walls that were cracked and pulling away from fixtures, this school needed stabilization.
Solution: Pier Masters studied and prepped the area then they stabilized and lifted the school. 15 Atlas Piers were used to lift the school an average of an inch per pier.
Before:
After:
Study 95001 - Soil Nails
Problem: The backside of the residence was being hit by falling rock and landslides.
Solution: Excavation around the site was carefully done to expose the most solid surface of the wall and earth to effectively install the soil nails: the reinforcing mesh and rebar for the structural gunnite wall, the geotextile drainage mat, the 240 lineal feet of French drain, and the gunnite covering to the new reinforced wall.
Before:
After:
Study 20001 - Cracked Basement Floors and Sunken Walls
Problem: This home had huge cracks in the basement floor as well as sunken basement walls.
Solution: Pier Masters recommended ATLAS PIERS. Atlas Piers offer rapid installation (even in congested work areas), heavy load-bearing capacity, minimal disruption to the structure, and low cost. 8 piers were installed and the structure was lifted and stabilized.
Before:
After:
Study 21008 - Commercial Piering and Mudjacking
Problem: This commercial building was experiencing structural damage from being built on poorly compacted soil. Elevations were taken and revealed that the southeast corner and the south wall of the building had settled.
Solution: Caution was taken to carefully excavate and install eleven galvanized plate piers to stabilize and lift the structure as close as possible to its original position.
The interior floor was mudjacked to fill the void that had been created underneath. The floor was raised, and the void was filled.
Before:
After:
Study 20008 - Residential Piering 2
Problem: The foundation walls had settled almost six inches including the interior garage walls in this residence. The finished basement slab showed possible heaving in the center and the floor sloped toward the interior garage foundation walls. Sheetrock cracks had been patched throughout the home covering the underlying problem.
Solution: 32 Resistance piers and 3 helical piers were installed to correct the problem
Before:
After:
Join Us On: